Advice For Facing Brickwork

 

Home BondTen Points To Remember

We thank HomeBond, Construction House, Canal Road, Dublin for permission to reproduce this advice from HomeBond Issue No. 3 of November 1995

1. Always incorporate a D.P.C. tray in locations where any part of a building projects. e.g. Porch roofs, Bay Windows, changes in Roof Level, all Extensions whether Pitched or Flat roofs

2. Always incorporate a D.P.C. tray over a Lintel

3. Always install a Vertical D.P.C. at open reveals

4. Always provide a D.P.C. to bottom, back and ends of Brick Cills

5. Always fix window and door frames behind outer leaf

6. Always install a full metal tray D.P.C. in a Brick Built chimney

7. Always maintain the cavity.
Never use an insulation that bridges the cavity.

8. Always keep cavity clean.
Never allow mortar droppings to bridge cavity.

9. Always install the D.P.C. a min. of 150 mm above finished ground level.

10. Always fill cavity to a level between 150 and 225 mm below D.P.C.

We thank HomeBond, Construction House, Canal Road, Dublin for permission to reproduce this advice from HomeBond Issue No. 3 of November 1995

Ormonde Brick Ltd, Castlecomer, Co. Kilkenny, Ireland
Telephone +353-(0)56-4440350 | Fax. +353-(0)56-4441314 | Email: info@ormondebrick.ie
Registered in Dublin, No. 26941 | Registered Office : Castlecomer, County Kilkenny, Ireland