We thank HomeBond, Construction House, Canal Road, Dublin for permission to reproduce this advice from HomeBond Issue No. 3 of November 1995
|
1. Always incorporate a D.P.C. tray in locations where any
part of a building projects. e.g. Porch roofs, Bay Windows, changes in Roof
Level, all Extensions whether Pitched or Flat roofs

|
2. Always incorporate a D.P.C. tray over a Lintel

|
|
3. Always install a Vertical D.P.C. at open reveals

|
4. Always provide a D.P.C. to bottom, back and ends of
Brick Cills

|
|
5. Always fix window and door frames behind outer leaf

|
6. Always install a full metal tray D.P.C. in a Brick
Built chimney

|
|
7. Always maintain the cavity. Never use an insulation
that bridges the cavity.

|
8. Always keep cavity clean. Never allow mortar
droppings to bridge cavity.

|
|
9. Always install the D.P.C. a min. of 150 mm above
finished ground level.

|
10. Always fill cavity to a level between 150 and 225 mm
below D.P.C.

|